Electrical And Fuel Inlet Locations - GE 60000 Series Installation And Start-Up Manual

Hide thumbs Also See for 60000 Series:
Table of Contents

Advertisement

Available languages

Available languages

Concrete Slab
At the appropriate location, construct a concrete slab:
• 28 day compression strength of 3000 psi (200 MPa)
• Minimum 5" (13cm) thick
• Minimum 6" (15cm) wider than enclosure on all sides
(shown as D in figure)*
D
• Strengthen slab with No. 6 reinforcing bars (on
12" (30.5cm) centers) or 8 ga. steel wire fabric (6"
(15cm) centers).
Avoid placing reinforcement in entrance stub-up area (shown
as (B ).
B
Attach unit to slab at four corner locations (A) with minimum
5/16" diameter (8mm) (per local requirements) masonry
anchor bolts long enough to secure the unit.
The fuel inlet location (C) ,the concrete slab,
C
exhaust outlet (E) are shown for reference.
E
• The standby generator enclosure F measures
96" (243 cm) X 37" (94 cm).

Electrical and Fuel Inlet Locations

A through-slab power cable stub-up is preferred (see
figure above). If stub-up's are not used, (F) indicates the
recommended location for punching holes for attaching
power conduit. The 1 inch N.P.T. fuel inlet connector (C) is
shown for reference.
A
and the
D
F
F
C
7-1/2"
19cm
14-3/4"
37.5cm
6"
15.2cm
51"
129.5cm
92"
233.7cm
A
A Holes located in base to anchor to pad
B
B Stub up Area
C
C Fuel Inlet
D
D Concrete slab
E
D Exhaust Outlet
F
D Standby Generator Enclosure
34-1/4"
87cm
5"
12.7cm
A
B
C
F
D
E
F
C
15

Advertisement

Table of Contents
loading

Table of Contents