Huawei FusionCol8000-E400 Quick Manual page 4

Hide thumbs Also See for FusionCol8000-E400:
Table of Contents

Advertisement

Requirements for Maintenance Space
2.3
Unit: mm
(1)Wall
(2)Electric control box
3
Securing the FusionCol8000-E
1. Read the related user manual before installing the device.
2. Ensure that the concrete platform levelness meets the requirements before installation.
3. It is recommended that the strength of the concrete foundations be at least C20 and
the load-bearing capacity of the ground be greater than or equal to 500 kg/m
Concrete Platform Scenario
3.1
• When marking the mounting positions for concrete platforms, ensure that the four lines form
a rectangle.
• When the equipment is installed indoors, it is recommended that shock pads be installed.
• It is recommended that the strength level of the concrete foundation be C20 or higher.
1. Determine the location of concrete platforms according to the site space and equipment
dimensions. Mark the reference points of concrete platforms using an ink fountain and
measuring tape.
Separate Installation
Unit: mm
(1) FusionCol8000-E
(2) Concrete platform
3
2
.