Settings

Mandatory settings

The system need to be set mandatory settings in following order when the system is turned on for
the first time.
Mandatory settings order : [PV/Meter] > [PCS] > [Network] > [Operating Test]
[PV/Meter] settings
You can check the PV and Meter information.
3
NOTE
The [PV System Capacity] options of [PV1], [PV2] and [PV3] are the mandatory options for
operating test.
Tap [PV/Meter] on [Installer Settings]. PV and
energy meter information is displayed.
[PV], [PV1], [PV2] and [PV3]
1. Select the currently selected value of each
option to change. Input menu appears on the
screen.
2. Input the desired value.
3. Select [Accept] to complete the setting.
[Meter]
1. Select the currently selected value of each
option to change. Input menu appears on the
screen.
2. Input the desired value.
3. Select [Save] to complete the setting.
Tap [Start Auto] to collect the connected energy
meter information and set all the option values
automatically.