After the PDU2000-M (C) is powered on, the LCM displays the initialization
−
screen.
Figure 5-10 PDU2000-M (C) initialization screen
Press MENU to enter the device communications address screen.
−
Figure 5-11 PDU2000-M (C) communications settings
−
Set address to 1 by pressing DOWN and UP.
−
Press MENU to confirm the settings.
The parameter settings take effect only if you press MENU and then the PDU2000-M (C) buzzes and
restarts. If you do not press MENU, the PDU2000-M (C) buzzes and restarts automatically after 30s and
the settings are not saved.
Set the PDU2000-M (H) monitoring parameters.
The display of a single-phase module is used as an example.
−
After the PDU2000-M (H) is powered on, press MENU. The LCM displays
.
−
Press MENU again to access the device communications address screen.