Installing, connecting up and commissioning the module
Note
Connection with power off
Only wire up the S7-1200 with the power turned off.
Table 4- 2
Procedure for installation and connecting up
Step
What to do
1
Mount the CP on the DIN rail and connect it to
the module to its right.
2
Secure the DIN rail.
3
Connect the Ethernet cable to the CP.
4
Turn on the power supply.
5
The remaining steps in commissioning involve
downloading the STEP 7 project data.
6
Close the front covers of the module and keep
them closed during operation.
Siemens Automation
CP 1243-1 PCC
Operating Instructions, 02/2015, C79000-G8976-C384-01
Installation, connecting up, commissioning
4.2 Installing, connecting up and commissioning
Notes and explanations
Use a 35 mm DIN rail.
The slots to the left of the CPU are permitted.
You will find the pinout of the interface in the section Technical
specifications (Page 61).
The STEP 7 project data of the CP is transferred when you
load to the station. To load the station, connect the engineer-
ing station on which the project data is located to the Ethernet
interface of the CPU.
You will find more detailed information on loading in the follow-
ing sections of the STEP 7 information system:
"Loading project data"
"Using online and diagnostics functions"