Toshiba 4400 Series Installation Instructions Manual page 2

Ups seismic adapter kit

Advertisement

15-30 kVA Seismic Adapter Kit (Cont.)
1. Prepare the floor anchorages. Arrange the anchorages to ac-
commodate the final layout including placement of ancillary bat-
tery and/or Auxiliary cabinets. (Figure 2)
2. Prepare the wall anchorages. Key measurements off the an-
chorage placement in Step 1. (Figure 3)
3. Table 1 lists the components of the 30kVA Seismic Kit. Figure 4
show the Seismic anchorage components in the Seismic Kit for
the 30kVA cabinets.
4. Assemble the fastener groups in Table 1, [4a-4c], [10a-10c], and
[11a-11c] as shown in Figure 1.
5. Secure the Top Seismic Bracket [1] to the top rear of the UPS
using two (2) fastener group [11]. (Figure 5)
6. Install the Base Brackets, [2], on the UPS base. Use two (2)
fastener group [10] for each bracket. (Figure 6)
7. Secure the Base Mounting Bracket, [3], to the floor anchors
installed in Step 1.
8. Roll the 15-30 kVA UPS cabinet between the two vertical sides of
the Base Mounting Bracket, [4]. (Figure 7)
9. Line up the UPS so the bolt holes on the Bottom Seismic Brack-
ets line up with the holes on the Seismic Base Plate vertical
sides.
10. Secure the UPS to the Seismic Base Plate using the remaining
eight (8) fastener group [11]. Insert the bolts through the Seismic
Bracket to the welded nuts on the Seismic Base Plate. (Figure
7)
11. Secure the Top Seismic Bracket, [1], to the wall anchors installed
in Step 2.
12. Once installation is complete, use the single Fastener Group [4]
to secure the door of the UPS. (Figure 8)
FIGURE 5: TOP SEISMIC BRACKET INSTALLATION
2
11
1
11
4400 Series UPS Seismic Kit Installation Instructions – 94016-001
10.05 in
(255 mm)
5 in (127 mm)
1/4" Bolt
Anchor (2)
9.27 in
(471 mm)
Base Mounting Bracket
FIGURE 3: 15-30KVA SEISMIC
ANCHORAGE - WALL PATTERN
1
4
P/N 440300SEISMICKIT
FIGURE 4: SEISMIC KIT
COMPONENTS (15-30 KVA)
2
3