Note the following: WARNING Siemens products may only be used for the applications described in the catalog and in the relevant technical documentation. If products and components from other manufacturers are used, these must be recommended or approved by Siemens. Proper transport, storage, installation, assembly, commissioning, operation and maintenance are required to ensure that the products operate safely and without any problems.
Firmware version V3.0 Link between Industrial Ethernet and PROFIBUS with PROFINET IO functionality IE/PB LINK PN IO without bus adapter IE/PB LINK PN IO with bus adapter On the front of the housing, you will see the firmware version and the hardware product version printed as a placeholder "X".
Page 4
Product names and abbreviations ● LINK In this document, the name "LINK" is used in place of the full product name "IE/PB LINK PN IO". ● STEP 7 The short form of the configuration tool is used for the following products: –...
Page 5
You will find license conditions in the following document on the supplied data medium: ● OSS_IEPB-LINK_86.pdf Security information Siemens provides products and solutions with industrial security functions that support the secure operation of plants, systems, machines and networks. IE/PB LINK PN IO...
Page 6
In order to protect plants, systems, machines and networks against cyber threats, it is necessary to implement – and continuously maintain – a holistic, state-of-the-art industrial security concept. Siemens’ products and solutions only form one element of such a concept. Customer is responsible to prevent unauthorized access to its plants, systems, machines and networks.
Configuration and operation ......................45 Security recommendations ....................45 IP configuration ......................... 47 4.2.1 Configuring the IP address ....................47 4.2.2 Restart after detection of a duplicate IP address in the network.......... 48 IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 8
Replacing older modules ....................73 5.5.3 Replacing a module without PG/PC ..................74 SNMP ..........................75 Technical data........................77 Technical specifications of the LINK ...................77 Pinout of the Ethernet interface ..................79 Pin assignment of the PROFIBUS interface ................79 IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 9
Table of contents Approvals..........................81 Accessories ..........................85 BusAdapter ........................85 C-PLUGs........................... 86 Documentation references ......................89 /1/............................89 /2/............................90 /3/............................90 /4/............................90 /5/............................90 Index .............................91 IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 10
Table of contents IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
If you want to change the configured mode of the LINK, you need to clear/reset the LINK. Note that this deletes the configuration data, see also the section Clearing and for resetting to factory settings (Page 70). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 12
1.1 Application, modes and operating modes Gateway as PROFINET IO proxy Figure 1-1 IE/PB LINK PN IO as PROFINET IO proxy The LINK provides the connection between a PROFINET IO controller on Industrial Ethernet and PROFIBUS slaves visible as PROFINET IO devices via the LINK.
Page 13
1.1 Application, modes and operating modes Gateway in standard operation Figure 1-2 IE/PB LINK PN IO as gateway in standard operation In standard operation, the LINK supports the following functions: ● PG/OP communication, e.g. for loading programs and configuration data.
Page 14
After pressing the button the LINK is in maintenance mode for 10 minutes. The following functions are possible: – Restart – Resetting to factory settings To change from normal mode to maintenance mode using the button, refer to the section Maintenance mode (Page 28). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
– Slaves according to DP V1 ● Direct data exchange The LINK supports direct data exchange in its own DP Master system and in multimaster systems. ● PROFISAFE The LINK supports applications with PROFISAFE. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 16
● C-PLUG as exchangeable storage medium for configuration data The LINK supports storage of configuration data on the optional exchangeable storage medium C-PLUG. This simplifies replacement of a defective module by simply inserting the C-PLUG in the new module. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
The function is enabled as default. Characteristic Explanation / values Maximum number of connections to the PROFIBUS nodes Maximum data record size for parameters sent to 244 bytes PROFIBUS nodes via a connection IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
The LINK can be operated with the following C-PLUGs: ● C-PLUG 32 Memory: – Total capacity: 32 MB – Free capacity available: 30 MB ● C-PLUG 256 Memory: – Total capacity: 256 MB – Free capacity available: 126 MB IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
You can configure the LINK for all modes via Industrial Ethernet. If you use the device as a gateway in standard operation, it is also possible to download the configuration data via PROFIBUS. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 20
STEP 7 Basic / Professional V14 + Update • 1 + Support package 0192 Downloading the support package / HSP from the Internet You will find the HSP or support package on the following Internet pages of Siemens Industry Support. ● STEP 7 V5.x Link: (https://support.industry.siemens.com/cs/ww/en/view/23183356) ●...
LEDs, connectors, buttons LED displays of the LINK LEDs of the module Figure 2-1 LEDs of the IE/PB LINK PN IO The module has the following LED groups for displaying the status: Meaning ① Top LED strip The LEDs show the basic statuses, see table below, ②...
Page 22
Display of the operating and communications statuses The LED symbols in the following tables have the following significance: Table 2- 4 Meaning of the LED symbols Symbol LED status ON (steady light) Flashing LED status not relevant IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 23
Running (RUN), Ethernet connec- tion at port, no data traffic Running (RUN), problem with a module (DP slave) Running (RUN), module missing on PROFIBUS or is incorrectly configured (does not apply to PROFINET IO). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 24
(Page 71). Error loading firmware Status after failed firmware update When downloading firmware via PROFIBUS: Firmware is loaded after the restart. Loaded firmware not activated. Maintenance mode (after pressing the button) IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Ethernet connection at port 1, no data traffic Data traffic at port 1 No Ethernet connection at port 1 Ethernet connection at port 2, no data traffic Data traffic at port 2 No Ethernet connection at port 2 IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
The interface is constructed in the ET 200SP design and pin assignment. You will find further information in the catalog, in Siemens Industry Mall and in the system manual of the ET 200SP, see /4/ (Page 90) and in the appendix BusAdapter (Page 85).
The power supply is connected to the LINK with the supplied 4-pin plug-in terminal block. The plug-in terminal block is designed so that it can only be inserted in one position in the X80 socket of the LINK. The connector X80 has electronic reverse polarity protection. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Resetting to factory settings • Without any further actions, the LINK returns to the normal mode after 5 minutes. Maintenance mode Press the button for 1 second The maintenance mode is extended by 5 minutes. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 29
The LINK is reset to the factory set- onds tings. Note that configuration data is deleted when you reset, refer to the section Clearing and for resetting to factory settings (Page 70). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
The device may only be operated in an environment with pollution degree 1 or 2 (see IEC 60664-1). WARNING EXPLOSION HAZARD Do not press the button if there is a potentially explosive atmosphere. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 32
2 OR ZONE 2. WARNING When used in hazardous environments corresponding to Class I, Division 2 or Class I, Zone 2, the device must be installed in a cabinet or a suitable enclosure. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
This equipment is suitable for use in Class I, Division 2, Groups A, B, C and D or non- hazardous locations only. This equipment is suitable for use in Class I, Zone 2, Group IIC or non-hazardous locations only. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
The equipment is intended to be installed within an ultimate enclosure. The inner service temperature of the enclosure corresponds to the ambient temperature of the module. Use installation wiring connections with admitted maximum operating temperature of at least 30 ºC higher than maximum ambient temperature. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
3.2 Overview: Installation, configuration, commissioning Overview: Installation, configuration, commissioning Follow the steps as shown below. Installation and configuration can be performed independently of each other. Figure 3-1 Installing, connecting up and configuring the LINK IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
3. Connect the LINK to Industrial Ethernet via one of the RJ-45 jacks (X1). As an alternative you can use bus adapters at X3, that must be plugged in with the power turned off. When using bus adapters, the Ethernet interface X1 is inactive. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
LINK its PROFINET device name. ● Via PROFIBUS To download via PROFIBUS, you must first supply the LINK with the PROFIBUS address. For information on downloading see section Commissioning and startup of the LINK (Page 42). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Insert and remove only when power is off The C-PLUG must be inserted or removed only when the power is off! Figure 3-3 Left: IE/PB-LINK PN IO without C-PLUG / right LINK with C-PLUG IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 39
C-PLUG. configuration data is plugged in. The configuration data in the internal LINK is to run with data from the C- • memory is deleted. PLUG instead of with the internal data. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 40
If the C-PLUG has not been written to (factory status), when the device starts up all configuration data of the LINK is automatically backed up. Changes to the configuration during operation are also backed up on the C-PLUG. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 41
C-PLUG can only be read. To have configuration data transferred to it, this C-PLUG must be reformatted. Use only a C-PLUG that is formatted for the IE/PB LINK PN IO. A C-PLUG that has already been used in a different device type and that was formatted for this device type must first be formatted for the LINK.
In this mode. the following first step is necessary: ● Assign the LINK the PROFINET device name Following this you can take the following steps: ● Optional: Assign or change the IP address ● Download the configuration data IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 43
3. Now plug in the bus adapter connected to the network. 4. Turn on the power. Only now is the interface X3 of the bus adapter active and the ports X1P1R / X1P2R of the integrated Ethernet interface are deactivated. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
During startup the configuration data is once again downloaded from the PROFINET IO controller. • LINK in standard mode All stored data is retained after turning off the power and when the power is turned on the LINK starts up as configured. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
● Keep the firmware up to date. Check regularly for security updates of the firmware and use them. ● Check regularly for new features on the Siemens Internet pages. – Here you will find information on network security: Link: (http://www.siemens.com/industrialsecurity) –...
Page 46
DHCP 67 (UDP) Open Open 93 (UDP) Open Open 135 (TCP) Open Open HTTP 8080 (TCP) Open Open 123 (UDP) Closed Open after configuration S7 communica- 102 (TCP) Open Open tion IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
To do this, the MAC address of the interface or the client ID that can be entered in the configuration or the PROFINET device name is transferred to the DHCP server. You will find further information in the configuration manual for S7 CPs /3/ (Page 90). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
1. Connect the PC to the LINK. 2. Start the PST using the start menu: Siemens Automation > SIMATIC > Primary Setup Tool > Primary Setup Tool 3. First set the access point of the PC with: "Settings" > "Set PG/PC Interface"...
Page 49
Figure 4-1 Ethernet interface: Entering the IP address and subnet mask 5. Select the PROFIBUS interface. In the right-hand part of the window, the network settings of the PROFIBUS interface are displayed. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 50
The download of the Ethernet and PROFIBUS parameters to the LINK begins. During the download you receive to queries. 9. , Firm these queries with "Yes" if you want to transfer the configured parameters. Result: The parameters are downloaded to the LINK. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
For information on further configuration, refer to section Use only as a gateway in standard operation (Page 53). Note Support when configuring: Online help You will find detailed information on the procedure in the online help of STEP 7 V5.x. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
DP Master system, you must therefore first select the PROFIBUS submodule. 6. As far as necessary, set further properties of the LINK. 7. Configure the DP master system with its PROFIBUS nodes: IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
3. Insert the LINK from the hardware catalog in "SIMATIC 300" > "Gateway" > "IE/PB LINK PN IO". When you take the IE/PB LINK PN IO from the hardware catalog, you will be requested to network the LINK on the Ethernet and PROFIBUS interface.
Here, you can change the device numbers of the connected DP slaves. ● "Diagnostics" tab With a connected LINK, you can call up NCM special diagnostics. The ● "Identification" tab Here you configure I&M data of the LINK. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
2. Download the configuration data to the LINK. The first download must be from industrial Ethernet via the Ethernet interface. Depending on the PG/PC connection subsequent downloads can be from PROFIBUS or from Industrial Ethernet via the Ethernet interface. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
If, instead of direct connection of the Ethernet interface you want to use a bus adapter, follow the steps below: 1. Find the required bus module in the catalog of HW Config: PROFINET IO > Gateway > IE/PB Link PN IO > 6GK1 411-5AB10 > V3.0 > "Bus adapter" 2. Insert the bus adapter.
1. Create a STEP 7 project. 2. Insert a LINK from the catalog: "Network components" > "Gateways" > IE/PB Link PN IO > 6GK1 411-5AB10 For the further configuration as a PROFINET I/O proxy, refer to the section Use as a PROFINET IO device (Page 57).
Page 58
You configure the remaining parameters in the parameter groups of the LINK. Here, you can also change the PROFINET device name. For information on downloading and further commissioning, refer to section Commissioning the LINK as a PROFINET IO device (Page 60). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
3. Change to the device view. 4. Browse for the required bus adapter and drag it to a free slot for bus modules on the LINK. 5. Configure the port properties of the bus adapter. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
1. Download the configuration data as described above. 2. Turn off the power. 3. Plug in the bus adapter and connect it to the network. 4. Turn on the power. The ports of interface X1 are then disabled. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
M data is plant-dependent information, e.g. the plant designation and the location designation. Maintenance data is created during the configuration and written to the module. M data can be read and written. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 62
Reading the I&M data using STEP 7 Professional Gateway in standard operation Requirement: There must be an online connection to the LINK. 1. Select the LINK in the project tree. 2. Select "Online & diagnostics" > "Identification & Maintenance". IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 63
Reading/writing I&M data with the user program ● To read I&M data in the user program, use the the block SFB52 "RDREC". ● To write I&M data in the user program, use the the block SFB53 "WRREC". IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Article number of the module (here: bus adapter) IM_SERIAL_NUMBER Read (16 bytes) Serial number (device-specific) IM_HARDWARE_REVISION Read (2 bytes) Hardware product version IM_SOFTWARE_REVISION Read Firmware version Firmware version of the module (1 byte) SWRevisionPrefix • IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
65003). You will find more information on the data structure of DS 255 in the specifications of Profile Guidelines Part 1: Identification & Maintenance Functions - Order No. 3.502, version 1.2 from October 2009. Time-of-day synchronization Synchronization method The LINK supports time-of-day synchronization methods listed below. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 66
NTP server with stratum 16, the time of day is not set according to the frame. In this case, none of the NTP servers is displayed as "NTP master" in the diagnostics; but rather only as being "reachable". IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
: According to IEC 61158-x-10 changing the IP parameters of an IO device when a connection is established is not premit- ted. : Not supported for reasons of compatiblity. Reformatting the C-PLUG for IE/PB LINK PN IO V3 is permitted. There are restrictions in the following situations: ●...
Page 68
Configuration and operation 4.8 Overview: Access to the LINK as proxy IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
You will find further information on the diagnostics functions of STEP 7 in the STEP 7 information system. STEP 7 V5 Here, the known diagnostics tools are available to you. SNMP You will find detailed information about the supported functions in the section SNMP (Page 75). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Overview: Access to the LINK as proxy (Page 67), After resetting, the LINK only contains the MAC address (as shipped). The content of the C-PLUG is completely deleted, the formatting is retained. The LINK restarts. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
The LINK supports the loading of new firmware files by the firmware loader of STEP 7. If a new firmware version is available for the module, you will find this on the Internet pages of Siemens Industry Online Support: Link: (https://support.industry.siemens.com/cs/ww/en/ps/15406/dl) The PG/PC must be connected to the LINK via a direct point-to-point connection via PROFIBUS.
Page 72
The firmware loader is installed, along with STEP 7 V5. Open the firmware loader from the Windows Start menu: "Siemens Automation > SIMATIC > STEP 7 > NCM S7 > Firmware Loader" You will find more information in the online help of the firmware loader.
The MAC address is stored permanently on the LINK and is not deleted when you reset to the factory settings. 5.5.2 Replacing older modules Replacing a module The LINK (6GK1 411-5AB10) can be used as a replacement for the following predecessor products: ● 6GK1 411-5AB00 IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
An existing module is replaced by a new module with a new configuration. If adaptations are made to the configuration, the IE/PB LINK PN IO can be used instead of a module with firmware version V2.x or V1.0. The LINK used previously is replaced by the new LINK in the configuration: Load the new configuration on the new module.
Range of performance of the LINK The LINK supports data queries using SNMP in version V1 (standard). The LINK returns the content of certain MIB objects according to the MIB II standard and the part of the Siemens Automation MIB relevant for the LINK.
Page 76
The LINK uses the following community names to control the access rights in the SNMP agent: Table 5- 1 Access rights in the SNMP agent Type of access Community name Read access public Read and write access private *) Note the use of lowercase letters! IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
≤ 95 % at 25 °C, no condensation Operating altitude During operation ≤ 2000 m above sea level at max. 60 °C ambient temperature Contaminant concentration Acc. to ISA-S71.04 severity level G1, G2, G3 Design, dimensions and weight IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 78
ET 200SP" applies to the LINK: ● Electromagnetic compatibility ● Transportation/storage conditions ● Mechanical and climatic environmental conditions ● Information on insulation checks, protection class and degree of protection For the system manual see /4/ (Page 90). IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Contacting the shield of the PROFIBUS cable The shield of the PROFIBUS cable must be contacted. To do this, strip the insulation from the end of the PROFIBUS cable and connect the shield to functional earth. IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 80
Technical data 6.3 Pin assignment of the PROFIBUS interface IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Germany You will find the EC Declaration of Conformity for this product on the Internet at the following address: Link: (https://support.industry.siemens.com/cs/ww/en/ps/15406/cert) Filter settings: Entry type: "Certificates" Certificate Type: “EU Declaration of Conformity" IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 82
Electromagnetic compatibility (EMC directive) The product meets the requirements of the EC Directive:2004/108/EEC "Electromagnetic Compatibility" according to the following standards: ● EN 61000-4 Emission - industrial area ● EN 61000-2 Immunity - industrial area IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 83
SIMATIC NET products are regularly submitted to the relevant authorities and approval centers for approvals relating to specific markets and applications. If you require a list of the current approvals for individual devices, consult your Siemens contact or check the Internet pages of Siemens Industry Online Support: Link: (https://support.industry.siemens.com/cs/ww/en/ps/15406/cert)
● BA SCRJ/FC PROFINET bus adapter, media converter FO - copper with the following connectors: – 1 x fiber-optic cable POF/PCF – 1 x direct connection of the bus cable (FastConnect) Article number: 6ES7193-6AP40-0AA0 IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
You will find the pinout of the Ethernet interface of the bus adapter with RJ-45 connector in section Pinout of the Ethernet interface (Page 79). You will find further details in the manual /4/ (Page 90) and in the Siemens Industry Mall. Link: (https://mall.industry.siemens.com)
Page 87
Number of write cycles: Max. approx. 200000 Recommendation: Avoid writing data cyclically. The flash area allows a limited number of write cycles. You will find further details in the Siemens Industry Mall. Link: (https://mall.industry.siemens.com) IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Documentation references Where to find Siemens documentation ● Article numbers You will find the article numbers for the Siemens products of relevance here in the following catalogs: – SIMATIC NET - Industrial Communication / Industrial Identification, catalog IK PI – SIMATIC - Products for Totally Integrated Automation and Micro Automation, catalog...
Page 90
Documentation references B.2 /2/ SIMATIC NET IE/PB Link PN IO (6GK1 411-5AB00) Operating Instructions (2005) Siemens AG Link: (https://support.industry.siemens.com/cs/ww/en/view/19299692) SIMATIC NET S7 CPs for Industrial Ethernet Configuring and Commissioning Manual Part A - General Applications Configuration Manual Siemens AG Link: (https://support.industry.siemens.com/cs/ww/en/view/30374198)
Starting up the LINK, 42 STEP 7 version, 20 Support package, 20 Identification data, 61 IP address From DHCP server, 74 IP configuration, 15 Time synchronization, 16 Maintenance mode, 14, 27, 28 IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...
Page 92
Index IE/PB LINK PN IO Operating Instructions, 11/2017, C79000-G8976-C393-02...