Procedure
Step 1 Strip an appropriate length of the insulation layer using a wire stripper, as shown in Figure
4-2.
Figure 4-2 Stripping a PE cable (unit: mm)
Step 2 Insert the bare cable cores into the OT terminal and crimp them by using a crimping tool, as
shown in Figure 4-3.
Figure 4-3 Crimping the cable (unit: mm)
Step 3 Remove the screws, spring washers, and flat washers from the ground point.
Step 4 Install the crimped OT terminal, flat washer, and spring washer onto the screw, and tighten
the screw to a torque of 1.4 N·m using a torque screwdriver, as shown in Figure 4-4.
(2016-06-20)
Ground cable: outdoor copper-core cables with a cross sectional area of 4–6 mm
12–10 AWG are recommended.
OT terminal: M6
The length of removed insulation layer (L2) must be 2–3 mm longer than the cable crimping length of
the OT terminal (L1).
The cavity formed after the conductor crimp strip is crimped must wrap the core wires completely. The
core wires must contact the terminal closely.