To install the cable to the terminal strip follow these steps:
1. If an outer jacket is on the power cable then strip off about 25 mm (1
2. Strip 6 mm (0.25 in) of insulation from each of the conductors that
3. Crimp a ring or spade lug to each of the conductors using the crimp
4. Open the hinged protective cover over the power and relay terminal
5. Place each lug under the proper screw on the power terminal strip
Figure 2-13: Power Connections 6. Close the hinged protective cover over the terminal
20
in) of outer insulation from the cable.
will be connected to the power terminals.
tool.
strip.
(see Figure 2-13) and use the screwdriver to tighten the screw.