1
I N S TA L L AT I O N I N S T R U C T I O N S F O R N E M A S I Z E 3
300/400-line combination magnetic starters
Coil
A
Magnetic
assembly
Adjustment
dial
Overload relay
Figure 1 — reference diagram (representation only)
CAUTION
Before installing in a nuclear application,
determine that the product is intended
for such use.
WARNING
Disconnect power before installing
or servicing.
Ratings
Max.
Max.
continous
voltage
amp rating
AC volts
600
90
115
200
230
460/575
Description
An ABB 300-line full voltage magnetic
combination starter consists of a
magnetic contactor with a three-leg block
Coil retainer
B
A
Magnetic assembly
Adjustment dial
Heater slots
Overload relay
Figure 2 — reference diagram (representation only)
overload relay and a manually operated
circuit breaker or disconnect switch. The
disconnect switch may either be fusible
or non-fusible. The non-fusible disconnect
switch provides a means of manually
disconnecting the motor from the line.
The circuit breaker or fusible disconnect
switch provides motor branch short-
circuit protection. The overload relay
provides motor protection against
running and stalled motor overload.
The overload relay is provided with a
yellow trip indicator, located to the right
of the reset arm and visible when the
overload relay is tripped.
Max. HP for AC motors
Single-
Poly-
phase
phase
Features
7
1
2
1. Strongbox coil.
25
2. Overload relay, incorporates a dial
15
30
50
for ±10% field adjustment of tripping
current, so that it is no longer
necessary to change heaters to
eliminate such problems as nuisance
tripping in hot weather.
3. Overload trip indicator.
4. Straight-through wiring.
5. Oversized power terminals will
accommodate up to 1/0 AWG.
6. Starter can be disassembled and
inspected in a matter of seconds.
Fusible disconnect
switch
7. Circuit breaker or disconnect switch
is mechanically interlocked with the
Fuse clip block
enclosure door to prevent opening
the door until the handle is moved
to the OFF position.
Spring clip
Coil retainer
Installation
Before connecting the starter:
1. Remove all packing.
2. Clean magnet mating surfaces
OL relay heater slots
of any dust or foreign matter.
3. Select heaters in accordance with
heater table, which accompanies
each device.
4. Operate movable magnet and
operating arm by pressing on the
nameplate to assure free movement.
5. Mount the starter on a sturdy
vertical support.
6. The overload relay may be reset
manually by depressing and releasing
the reset arm. Overload relays with an
optional normally open contact are
electrically isolated from the normally
closed contact.
7. Provide motor branch circuit protection
in accordance with the National
Electrical Code.
Coil removal
The encapsulated coil is impervious to
moisture, dirt and oil. It resists mechanical
damage and failure due to high humidity.
No tools are required to remove coil.
1. Remove power from device.
2. Press against coil while pulling up
slightly on coil retainers (A—Figure 1)
and move retainers away from coil.
3. Withdraw magnet assembly, coil,
molded cover and movable arm
from device.

Advertisement

loading

Summary of Contents for ABB 300-line

  • Page 1 (A—Figure 1) Description eliminate such problems as nuisance and move retainers away from coil. An ABB 300-line full voltage magnetic tripping in hot weather. 3. Withdraw magnet assembly, coil, combination starter consists of a 3. Overload trip indicator.
  • Page 2 Check for welded contacts Simple maintenance 4. Withdraw spring clip (B—Figure 1) and in overload relay remove armature from movable arm. 300/400-line starters and contactors 5. Remove coil from magnet. This feature permits maintenance require virtually no corrective 6. Replace coil. personnel to check for welded relay maintenance.
  • Page 3 Cary, NC 27511 to purchase orders, the agreed particulars utilization of its contents – in whole or in shall prevail. ABB Inc. does not accept any parts – is forbidden without prior written responsibility whatsoever for potential consent of ABB Inc. Copyright© 2021 ABB.

This manual is also suitable for:

400-lineNema size 4